Skip to main content

Quant Analytics: from scratch to pro · Portfolio, sizing and risk metrics · Intermediate

Value at Risk and expected shortfall

Value at Risk names a loss level that is exceeded on a small share of days. Expected shortfall averages the losses beyond it. Banking regulation moved from the first to the second for internal models, for reasons this lesson works through.

3 min read Reviewed Revision 1

In this lesson

  • Compute parametric value at risk and expected shortfall under a normal assumption
  • Compute both from a sample of historical returns
  • Scale a one-day figure to a longer horizon and say when that fails
  • Explain why expected shortfall replaced value at risk in the Basel internal models approach

Read first: Volatility: from daily moves to an annual figure, Return distributions and fat tails

Normal VaR and ES multipliers against confidence level

  • VaR
  • expected shortfall
1.0 1.5 2.0 2.5 3.0 0.90.9250.950.9750.990.995 Confidence level
Multiple of daily volatility. Computed under a normal distribution with zero mean. ES lies above VaR at every level. With fat tails, real ES exceeds the normal figure by more.

Worked numbers

Each result is recomputed from the formula shown.

WhatFormulaResult
99% normal quantilephi_inv(0.99)2.326
99% one-day VaR on 1,000,000, volatility 1.2%z99 * 0.012 * 100000027,916
97.5% normal quantilephi_inv(0.975)1.960
97.5% VaRz975 * 0.012 * 100000023,520
97.5% expected shortfall0.012 * pdf(z975) / 0.025 * 100000028,054
99% expected shortfall0.012 * pdf(z99) / 0.01 * 100000031,983
10-day 99% VaR by square-root scalingvar99 * sqrt(10)88,279
average of the ten worst daily losses, in percent of value(6.0 + 5.1 + 4.4 + 4.0 + 3.7 + 3.5 + 3.4 + 3.3 + 3.2 + 3.1) / 103.97

Check yourself

A portfolio of 500,000 has daily volatility of 1%. What is its one-day 99% normal VaR?

2.326 x 1% x 500,000 = about 11,632. On about 1 day in 100, the loss is expected to be at least this large.

Does a 99% VaR of 11,632 say the loss cannot exceed that figure?

No. It is a threshold, not a maximum. It says nothing about how large losses are once past it.

Why do two portfolios with the same 97.5% VaR have different expected shortfall?

Expected shortfall averages the losses beyond the VaR level. A portfolio with a fatter or longer tail has the same threshold but a larger average loss past it.

You have 1,000 daily returns. How do you read the historical 99% VaR and ES?

Sort the losses. VaR is the 10th worst loss, ES is the average of the 10 worst.

Why is square-root-of-time scaling of a one-day VaR to ten days only an approximation?

It assumes independent days with constant volatility. Volatility clustering and autocorrelation break both assumptions, usually making the real ten-day tail heavier.

Key terms

Value at RiskExpected shortfallTail riskStandard deviation

Checked facts

Every figure below carries how it was checked: Primary checked (read in the cited primary, official, academic or data source), Two sources agree, or Approximate (an order of magnitude only).

  • Primary checked

    Under the Basel Committee's revised market risk framework, internal models measure risk with expected shortfall at a 97.5% confidence level, replacing value at risk.

    As of Jan 2019. Source: Minimum capital requirements for market risk (d457).

Sources

  • Minimum capital requirements for market risk (d457). Basel Committee on Banking Supervision, Bank for International Settlements, 2019. Accessed 9 Nov 2026
  • Coherent Measures of Risk. Mathematical Finance 9(3), 203-228 (Philippe Artzner, Freddy Delbaen, Jean-Marc Eber, David Heath), 1999. Accessed 9 Nov 2026
  • Techniques for Verifying the Accuracy of Risk Measurement Models. Finance and Economics Discussion Series 95-24, Board of Governors of the Federal Reserve System (Paul H. Kupiec), 1995. Accessed 9 Nov 2026

Informational content. Not investment advice.